Kurdistan cement grinding

Start Date: July. 23, 2013
Ending Date: Sep. 23 , 2014
Contract Subject: Extension for mixed cement and hydrated lime
Employer: Kurdestan Cement co
consultant: Rahbordsanat Engineering Services Co.
Project Place:Bijar – Iran


description:
Work shop inspection and supervision for equipment and steel structure manufacturing. Determination of project work breakdown structure. Coding system design. Preparing 3rd level activity list plus critical path. Calculating weight factor for each activity. Estimation of project meeting Preparing monthly budget Analytical project report Project progress curves